Group Eight Engineering Limited

Taylor Steel Inc., Plant No. 7, Hamilton

New Steel Warehouse Facility

Group Eight Engineering Limited was the Prime Consultant, providing architectural, structural, mechanical and electrical engineering services for this new state-of-the-art steel coil storage facility.

The facility is approximately 180,00 ft2 and was designed to allow a 120,000 ft2 expansion.

The facility was designed to handle a heavy volume of steel coil product and is equipped with large, high-speed, automatic overhead doors and eight, 45-tonne overhead cranes with a hook height of 28 ft. Four large, direct-fired, continuously operating, exterior heating/ ventilating units maintain a constant positive pressure within the building. Very tight dew point and temperature control is required for the storage of "Class I Automotive" steel coils.

Due to the large volume of truck traffic, CO and NO2 gases are also monitored, and ventilation provided to "purge" the building as necessary.

The facility contains a Lunchroom, washrooms, and shower and change areas for the employees.


Round-the-clock, high volume, crane operation requires very tight building and crane operating tolerances.
The ventilation, interior pressure, dew point and temperature levels are constantly monitored by computer.

  Group Eight Engineering Limited

Top of Page


For higher resolution printing purposes, this experience sheet is available in PDF format. If you are using Microsoft Internet Explorer, place your cursor over this link and press the right mouse button. Choose  "Save Target As" and save it to your computer's hard drive.  If you are using Netscape, follow the same steps as above, but choose "Save Link As".

The Adobe Acrobat Reader is required to view PDF files and may be downloaded at no cost from www.adobe.com.

Get Acrobat


Profile | Services Available | Structural | Mechanical | Electrical | Experience | Contact Us | Home |Previous Page
Copyright
© 2000 Group Eight Engineering Limited. Last Revised: June 30, 2004